Avery Substation Project

Avery Substation Project

Project Updates

January 2022 Construction Update 

Recently completed activities:

  • Installation of the remaining transmission line foundations.
  • Installation of erosion control measures and transmission line access improvements north of County Road 78.

Current activities:

  • Equipment delivery and placement continues, and trucks may be seen coming on and off County Roads 13 and 76.
  • Materials continue to be delivered to the staging area immediately south of the substation site.
  • Installation of underground vaults and wire conduit for electrical distribution equipment from Latham Blvd. east to the substation driveway and up the west side of the substation driveway to the substation will continue through March 2022.
  • Installation of transmission line structures north of County Road 78 will continue through early March.

Substation construction began in early 2021 and we anticipate completing the work by Summer 2022. Construction schedules may change. Visit xcelenergy.com/Avery for up-to-date information.

Staying safe around construction areas

For your safety and the safety of our crews, take the following steps near work areas:

  • Be alert and look for crews and equipment.
  • Do not enter work areas.
  • Follow construction signage and directions from crews.
  • Reduce speeds when driving through work areas.

Project Overview

The new Avery Substation will add capacity to deliver reliable, safe electric power to a fast-growing area of Northern Colorado. Proactive planning for current and future growth will help reduce the risk of electric outages and improve grid reliability while meeting needs for years to come. The new Avery substation will serve homes and businessess in and around Windsor, Severance and Timnath. View benefits.

The Avery Substation Project includes several components:

  • A new electric distribution substation located in the Town of Windsor
  • Overhead double-circuit 230-kilovolt (kV) electric transmission line (0.5 miles in unincorporated Weld County, 0.4 miles in Town of Severance and 0.4 miles in Town of Windsor)
  • New distribution lines and upgrades to existing distribution lines near the towns of Windsor, Severance, and Timnath, Colorado.
  • Power for the proposed 1.3 mile 230-kV transmission line will be provided by interconnecting with the existing Platte River Power Authority (PRPA) Timberline-Ault 230-kV transmission line. This connection will supply the proposed Avery Substation with the electrical supply needed to power the distribution feeders serving the surrounding communities.

Project History

We have worked with the community on this project since 2012. We invited over 1,700 landowners and stakeholders to attend the public open house on July 9, 2019. Attendees were asked for feedback on two potential sites for the substation and transmission line extension in Windsor, both on property owned by the City of Thornton. Since the public open house, we have identified the West Site, located northeast of the intersection of Weld County Road 76 and Latham Parkway in Windsor as the project location (PDF). We chose the West Site location because it offers a wide range of benefits and is the preferred site based on recent public feedback.

The Town of Windsor approved the Conditional Use Grant permit application for the West Site in November 2019. Additional details about the Town of Windsor Planning Commission and Town Board approvals can be found on the Town of Windsor website (external link).

Site Information

Distance

The substation is located more than 1,500 feet away from adjacent subdivisions to reduce the visual scale of the facility.

Wetlands and wildlife

The substation maximizes distance from wetlands near Lee Lake and near Weld County Road 76 that may support wildlife.

Screening

The substation uses existing vegetation, topography, and distance to reduce the visual impact of the facility and will also incorporate additional landscape screening in the site design.

View simulations

Transmission line

The substation includes a straighter path for the transmission line and minimizes the number of large support structures, while increasing the distance of the transmission line from the majority of viewers.

Community preferred

The substation is consistent with the consensus of those attending and commenting on the project during the July 2019 public open house for the reasons outlined above.

Contact Us

Please call the project hotline at 833.539.0506 or email info@xcelenergyaverysubstation.com with any questions or concerns. You can also sign up to receive project updates by email here.